Click to Home

Go To Search
HomeEmailPrintRSSFacebookTwitter
Emergency Alerts Inactive
525 San Anselmo Avenue
San Anselmo, CA 94960
Ph: (415) 258-4600
Fx: (415) 459-2477
Current Projects
Localized Pavement Repair

PLEASE USE CAUTION AND FOLLOW TRAFFIC CONTROL WHEN DRIVING THRU ALL CONSTRUCTION SITES.

Other road closure notifications will be issued as necessary and in advance of the work.  The slurry schedule will be announced once it is finalized.

In addition 

to our pavement rehabilitation project for 2014, the Town performs asset protection in the form of preventive maintenance such as a slurry seal. It is less expensive to prolong the life of good asphalt with maintenance, then to wait until it deteriorates so far that it needs full replacement. Preventative maintenance is a cost effective way to extend the life of the pavement saving both cost and environmental impact.

During August 2014, we anticipate a two day slurry project. The streets tentatively scheduled for this work are:

Woodland Avenue (between Cedar and San Anselmo ave)

Ross Aveue (between Cedar and San Anselmo ave)

Tunstead  Avenue

Sequoia (between Milbrae and Hilldale)

Jones Street

Raymond (Bolinas to Mariposa)

Miwok Drive

Nokomis Avenue

 

During September 2014, we anticipate a one day slurry project. The streets tentatively scheduled for this work are:

Broadmoor Ave

Brookmont Circle

 


As you can see from the list, these streets are in fairly good to very good condition. This is the right time to apply a slurry seal. The slurry seal will help protect the asphalt from ultra violet and rain infiltration which cause further cracking and deterioration. These streets have already received rubberized crack seal treatment for major cracks. Several of these streets have localized areas of pavement failure. In July, contractor crews will be removing and replacing these localized areas in preparation of the slurry seal.

Thank you for your patience and understanding.

 

 




2014 LED Street Light Retrofit Project


There are 411 high pressure sodium (HPS) street lights throughout the Town of San Anselmo.   The 2014 LED Street Light Retrofit project  will convert these street lights to energy efficient Light Emitting Diode (LED) lights that will greatly reduce the Town’s energy consumption while at the same time maintaining existing light levels.  The proposed project is in accordance with the Town’s Climate Action Change Plan and will reduce Green House Gas Emissions by approximately 140,000 lbs CO2 per year, removing the equivalent of 12 cars off the road per year. 

Conversion of the street lights to LED by the Town’s contractor DC Electric, Inc. will begin the week of June 30, 2014.  The work is expected to take 3 weeks to complete during which time there will be construction traffic controls, lane closures and parking restrictions at various locations around Town between the hours of 8:30am and 5:00pm.  Conversion of lights on Sir Francis Drake Boulevard and Red Hill Avenue maybe completed at night to avoid traffic interruptions.  A map of the existing street lights to be converted is available at: https://batchgeo.com/map/97ab43506007e5d22b9818d83c956267


Please contact the Town’s Project Manager by phone at (415) 258-4654 or by email at 
if you have any questions.

Safe Routes to School

Project Location Map
Concept Exhibits
Brookside School Sidewalk Concept


Give us Feedback: Vote here

2014 Street Rehabilitation Project

The Town is designing for the 2014 Street Rehabilitation project. The project scope includes repaving the following streets:  The Alameda from Arroyo to the Town Limits, Sunview Avenue, Toyon Terrace, Berkeley Avenue from Sunview to Broadmoor, and Oak Knoll Avenue.

Bid Results

Addendum 1 Part A

Addendum 1 Part B

Bid Holders List

Notice to Bidders

Town of San Anselmo, Capital Improvements Project Schedule in coordination with RVSD, MMWD and PG&E


2014 Capital Improvement Project Updates

May 30, 2014
March 24, 2014




2014 Utility Projects

MMWD - Replacement of Watermain

a) Greenfield Ave between Spring Grove and Sequoia

b) Bridge Ave

c) Sunview Ave

RVSD - Replacement and/or repair of Sewer System

FY 2014 Gravity Sewer Rehab Project Public Notification  

a) Sir Francis Drake Blvd (Pastori Ave to Kent Ave)

b) Monterey Terrace

c) East Court to Fairview Court (easement)

d) Scenic Ave

e) Crescent Rd

f) Roger Ave

g) Greenfield Ave (Greenfield Court to Terrace Ave)

PG&E

a) Oak Knoll Ave

b) Sunview Ave

c) Floribel (No.40 to No.101)


Berkeley Ave and Sunview Ave - PG&E Community Notice

Oak Knoll Rd - PG&E Community Notice

PG&E and its contractor, PAR Electric, will be starting work next week at various locations in the vicinity of downtown.  The work will include replacement of several utility poles and service conductors.  The locations and dates of work are as follows:


Location

Street or Nearest Cross Streets

Date

6

804 San Anselmo Ave

3/17/2014

5

114 Sycamore

3/18/2014

8

36 Ross Ave

3/19/2014

4

118 Sycamore

3/19/2014

8

36 Ross Ave

3/20/2014

1,3

126 and 130 Sycamore

3/20/2014

7

12 Tamalpias

3/21/2014

 

 
Town staff has reviewed and approved the traffic control plans and has coordinated with the Fire Department for the work in front of their station on San Anselmo Avenue.  The work on San Anselmo Avenue, Ross Avenue and Tamalpais will not require lane closures.  The work on Sycamore Avenue will require the contractor to shut the westbound lane on Center Boulevard between the hours of 9:00am and 3:00pm on the days of work.  This was the preferred alternative to working on Sycamore Avenue, which would require substantial trimming of the existing trees between Sycamore and Center.  PAR Electric will be installing changeable message signs at 74 Sir Francis Drake and on Red Hill Ave (the reference address is 2222 Greenfield Ave, but the sign is actually on Red Hill.).  Signs will inform the public to expect delays and the dates of work.