Tentative schedule as follows:
Work for the week of October 14-18 includes:
- Begin filling bio-retention pits
- Finish & fine grading of swales
- Install irrigation piping
The work started Wednesday August 28, continues thru mid-January. The majority of work to be completed by the end of December, with punch list items continuing into January.
Work hours 8 am to 5 pm, with any lane closures limited to 9 am to 3 pm.
Some elements of the work may require lane closures on SFD and Center, however, most lane closures will be on Red Hill.
This information will be updated as frequently as possible. Please plan your commute with this project in mind. The Town appreciates your patience during this project to help beautify the Town.